NetXMS Support Forum

English Support => General Support => Topic started by: pedrong on February 16, 2013, 08:11:27 AM

Title: Move/Copy Node from "Entire Network" to Infrastructure Services
Post by: pedrong on February 16, 2013, 08:11:27 AM
Hi All,

After network discovery there are a few nodes add to "Entire Network". Is it possible to copy/move this node to "Infrastructure Services"?

Thanks!!

Pedro
Title: Re: Move/Copy Node from "Entire Network" to Infrastructure Services
Post by: Victor Kirhenshtein on February 16, 2013, 09:02:05 PM
Hi!

It's called "bind". You can select "Infrastructure Services" object or any container below, choose "Bind..." from context menu, and select node(s) you want to put into container.

Best regards,
Victor
Title: Re: Move/Copy Node from "Entire Network" to Infrastructure Services
Post by: pedrong on February 17, 2013, 03:22:11 PM
hi Victor, Danke sehr!